top of page

ENABLING 
PROJECTS

Project: Tottenham Court Road

​

Scope: Enabling

​

Duration: 6 Weeks

Evolution were tasked with providing full welfare facilities for a central London site.

​

Works progress in conjunction with the adjacent demolition works and included:

​

  • Design of structural steel gantry

  • Design and formation of reinforced concrete ground beams

  • Traffic management design and implementation

  • Erection of all structural steel works

  • Fixing in place of units

  • Hoarding and cladding to beams, units and steel

​

The works were undertaken street side in Tottenham Court Road and required significant planning and co-ordination with the local authorities.

​

Works took place out of hours with numerous road closures for cranage and deliveries. Works were completed on time and provided our client with a structure ready to use on arrival.

Project: GMV CMS 

​

Scope: Enabling

​

Duration: 26 Weeks

Evolution Enabling were employed to undertake a fully encompassing service.

 

This consisted of: 
 

  • Full site set up as PC

  • Removal off-site of over 20,000m3 of spoil stockpiled from  historic phases

  • Full logistic set-up and supervision of all muck away              operations comprising of material surveying, testing,            weighbridge installation and management

  • Full groundworks and civils packages to prepare the site for the arrival of site concierge units

​​

Due to various works in the area under previous phases and differing main contractors, the logistic phase was particularly challenging. However, the spoil removal phase was completed on time and within budget without incident. The site was prepared for the arrival of the new development concierge suite, which included foundations, drainage, car park construction and external landscaping. Coupled with the contracted work additional works were awarded to facilitate the installation of further district heating networks, power, water and services supplies.

​

These works encompassed detailed traffic management planning with the local authority, the client and the various other contractors in the area. Deep excavations in the highways were designed, planned and managed to ensure safe works with all 278-works undertaken in house.

Project: HSQ3 

​

Scope: Enabling

​

Duration: 8 Weeks

​

Evolution Enabling were contracted to install the temporary access ramp into an underground carpark. The task included taking control and managing a live carpark during the construction.

 

The layout of the carpark had to be altered several times as the project commenced and progressed to allow the maximum availability of car parking spaces at all times, Evolution were contracted to employ a line painter to remove and install the segregation lines as required.

​

Following the enabling stage Evolution then handed over to our own Civil Engineering teams who then installed sheet piles down to a depth of 6000mm. With drainage in reinforced concrete to finish the ramp. 

Project: Esplanade Public House

​

Scope: Enabling, Demolition, Remediation 

​

Duration: 18 Weeks

Evolution Enabling Services was contracted in by Beyond the Box Developments as PC by competitive tendering to undertake demolition, and ground clearance of the Esplanade Public House on Southend-on-Sea Seafront to make way for a new high-end residential development. Due to arson prior to Evolution starting on site we were then called in as an emergency to make the fire-damaged steel frame structure safe once the Fire Services had finished their work.

 

Evolution Enabling scope of works thereafter was as follows:


• Design, Supply & Erection of site hoarding
• Vehicular & Pedestrian traffic management
• Controlled dismantling, demolition of structure using       

  conventional and robotic demolition techniques c/w full 

  environmental monitoring
• Temporary works to secure retaining wall (the building is at

   the foot of a steep cliff that has suffered landslides in the last

   twenty years towards the Seafront)
• Asbestos Removal
• Land Remediation
• Earthworks
• Concrete Crushing and Construction of piling mat with

  crushed material