Project: The Wispers

​

Scope: Enabling

​

Duration: 12 Weeks

​

Role: Principal Contractor 

Evolution where tasked with the de risking of a site prior to the approval of planning permission, the site contained a number of listed buildings, constraints due to ecological risk, significant tree works and access constraints. Works required the undertaking of extensive asbestos and ecological surveying as well as planning of future works to enable the application of local authority licences and Natural England permits. 

​

The Project required extensive pre construction coordination between the client, consultants and statutory bodies to ensure the complex works where planned correctly and programs and cost plan where put in place.

​

  • Listed buildings

  • Ecologyical surveying

  • Asbesto surveying

  • Pre construction planning

  • Securing of site

  • Consultant coordination

  • Planning and programming

Project: GMV CMS Relocation

​

Scope: Enabling

​

Duration: 15 Weeks

​

Role: Principal Contractor

Evolution where tasked with the relocation of the existing previously constructed management suite.

​

Employed as principal contractor and responsible for design and coordination of all works the moular units where stripped and prepared for lifting. The new location was prepared and infrastructure put in place to receive the units.

​

Lifting operations where planned and undertaken and the new units fitted out the the clients specification

​

  • Strip out and decommissioning

  • Civils and ground works

  • Lift planning and execution

  • fit out

  • External finishes

​

These works encompassed detailed traffic management planning with the local authority, the client and the various other contractors in the area. Deep excavations in the highways were designed, planned and managed to ensure safe works with all 278-works undertaken in house.

Project: Tottenham Court Road

​

Scope: Enabling

​

Duration: 6 Weeks

​

Role: Principal Contractor

Evolution were tasked with providing full welfare facilities for a central London site.

​

Works progress in conjunction with the adjacent demolition works and included:

​

  • Design of structural steel gantry

  • Design and formation of reinforced concrete ground beams

  • Traffic management design and implementation

  • Erection of all structural steel works

  • Fixing in place of units

  • Hoarding and cladding to beams, units and steel

​

The works were undertaken street side in Tottenham Court Road and required significant planning and co-ordination with the local authorities.

​

Works took place out of hours with numerous road closures for cranage and deliveries. Works were completed on time and provided our client with a structure ready to use on arrival.

Project: GMV CMS 

​

Scope: Enabling

​

Duration: 26 Weeks

​

Role: Principal Contractor

Evolution Enabling were employed to undertake a fully encompassing service.

 

This consisted of: 
 

  • Full site set up as PC

  • Removal off-site of over 20,000m3 of spoil stockpiled from  historic phases

  • Full logistic set-up and supervision of all muck away              operations comprising of material surveying, testing,            weighbridge installation and management

  • Full groundworks and civils packages to prepare the site for the arrival of site concierge units

​​

Due to various works in the area under previous phases and differing main contractors, the logistic phase was particularly challenging. However, the spoil removal phase was completed on time and within budget without incident. The site was prepared for the arrival of the new development concierge suite, which included foundations, drainage, car park construction and external landscaping. Coupled with the contracted work additional works were awarded to facilitate the installation of further district heating networks, power, water and services supplies.

​